An Analysis of the Early Prediction of Highway Construction Project Completion using the Contract Status Report

Authors
Gambill, Patti
South Carolina Certified Public Manager Program
Keywords
Roads--South Carolina--Design and construction , Express highways--South Carolina--Design and construction , South Carolina Department of Transportation , Project management--South Carolina , Road construction contracts--South Carolina
Abstract
History has shown that projects move in and out of poor status through the life of the project. Predicting the success or failure of a project to complete on time because of its recent history on the contract status report could provide our project managers another tool for monitoring contract progress. In many instances, poor contract progress results in the loss of contract time and late completion of projects. This research evaluates the combinations of work type, point in time physical work begins, recent poor status, and contract bid amount as indicators of late project completion.
Description
Loading...
Thumbnail Image
Issue Date
2016-02
Contributor
Date Accessioned
2016-09-28T12:22:02Z
Date Available
2016-09-28T12:22:02Z
Item Format
application/pdf
Media Type
Document
Item Language
English
Publisher
South Carolina State Library
Digital Collection
South Carolina State Documents Depository
Rights
Copyright status undetermined. For more information contact, South Carolina State Library, 1500 Senate Street, Columbia, South Carolina 29201.
Type
Text
Digitization Specifications
300ppi, Canon imageFORMULA DR-9050C scanner with CapturePerfect 3, archival and online file is PDF/A-1b.